How to calculate nail making machine productivity

Views: 0     Author: Rachel Bella     Publish Time: 2021-01-18      Origin: Original

Formula:  nail dia*nail dia*nail length (mm)*0.00000638*machine speed*60 minutes=XX kg/hour. 

For example:

2.5*70 mm nail, 2.5*2.5*70*0.00000638*750*60=125 kg/hour, 

3.5*130 mm nail,  3.5*3.5*130*0.00000638*650*60=396 kg/hour, 


Usually, when comes to high speed nail making machine output or speed, it talks about the productivity, and the high speed nail making machine manufacturer will indicate the maximum or highest speed to the clients. The actual production speed depends on the wire grade and adjustment of the high speed nail making machine, and there is a button on the PLC to control and set up the machine speed, it can be adjusted by the clients themselves.

 

7E7A2382


We have more than 60 well-trained skillful technicians, over 15000 square meters factory and equipped with high quality production&testing machines.
 

Quick Link

Contact us

 Subsidiary Company: Yanhuang Import and Export Trade (Shenzhen) Co., Ltd.
  Address: Room 826, Changsheng Building, Huaqiang North Road, Futian District, Shenzhen, Guangdong Province, China
  +86-755-28779462
 +86-515-88301532
 service03@ycyhzdh.com
+86 18018705289
  +86 18018705289    
   Sam Chen
All rights reserved Yancheng Yanhuang Automation Equipment Co., Ltd.